ContID 252024 EST NO 0004 |
Date:05/21/2025 |
COMMONWEALTH OF KENTUCKY
TRANSPORTATION CABINET
Contract ID | 252024 | Estimate Number | 0004 | Estimate Type | DRAFT_PROGRESS | ||
District Office | ELIZABETHTOWN (04300) Bagby, Brandon R. | ||||||
Contractor | LOUISVILLE PAVING COMPANY INC | MARS ADDR SN 0 | |||||
15415 SHELBYVILLE ROAD | |||||||
LOUISVILLE , KY , 40245 | |||||||
Pay Period | 05/03/2025 TO 05/16/2025 | ||||||
Date Approved | 05/20/2025 | ||||||
Primary Proj Number | MP04700652501 | ||||||
Project No. | NHPM 0653(051), NHPM 0653(049), NHPM 0653(050) | ||||||
Primary County | HARDIN | ||||||
Name of Road | SONORA TO ELIZABETHTOWN (I-65) | ||||||
Description | BEGIN AT THE LARUE/HARDIN COUNTY LINE EXTENDING NORTH TO NEW CONSTRUCTION JOINT 0.264 MILES NORTH OF COX RUN CULVERT | ||||||
Date Let | 01/23/2025 | Formal Acceptance | |||||
Date Awarded | 02/04/2025 | Date Work Began | 03/28/2025 | ||||
Date Contract Executed | 02/18/2025 | Open To Traffic | |||||
Date NTP Issued | 02/18/2025 | Actual Completion Date | |||||
Current Contract Amount | $7,068,217.75 |
Total to Date |
Prev to Date |
This Estimate |
||
Original Amount | $7,063,113.00 |
Total Earnings | $871,891.58 |
$547,987.57 |
$323,904.01 |
|
Percent Complete | 12.34 |
Stockpiled Materials | $0.00 |
$0.00 |
$0.00 |
|
Funds Available | $6,196,326.17 |
Gross Earnings | $871,891.58 |
$547,987.57 |
$0.00 |
|
Total Change Orders | $5,104.75 |
Other Adjustments | $0.00 |
$0.00 |
$0.00 |
|
TOTAL | $871,891.58 |
$547,987.57 |
323,904.01 |
|||
Contract Id | 252024 | Change Order Summary |
County | HARDIN | ||||||
Estimate Nbr | 0004 | Project Number | NHPM 0653(051), NHPM 0653(049), NHPM 0653(050) | |||||||
Contractor | LOUISVILLE PAVING COMPANY INC | Period | 05/03/2025 TO 05/16/2025 | |||||||
CHANGE ORDERS HISTORY | ||||||||||
CHANGE ORDER NBR | DESCRIPTION | STATUS | APPROVAL DATE | TOTAL CO AMOUNT | CONTRACT TIME ADJUSTED | |||||
001 | Queue Warning System | Approved | 04/29/2025 | $5,104.75 | 0.0 | |||||
CONTRACT ADJUSTMENTS HISTORY
Contract Adjustments |
|
|
Adjustment Description | Est No |
Adjustment Amount |
Line Item Adjustments History | |||||||||
PROJECT | ITEM NBR | DESCRPITION | TYPE | EST NO | ADJ QUANTITY |
UNIT PRICE |
ADJUSTED AMOUNT |
Contract Id | 252024 | COMMONWEALTH OF KENTUCKY |
County | HARDIN | ||||||
Contract Type | PALT PAVEMENT (WITH ALTERNATES) | TRANSPORTATION CABINET |
Primary Project Number | MP04700652501 | ||||||
Estimate Nbr | 0004 | Period | 05/03/2025 TO 05/16/2025 | |||||||
Contractor | LOUISVILLE PAVING COMPANY INC | |||||||||
Project | MP04700652501 | Fed/State Project Number | NHPM 0653(051) | Category | 0001 ROADWAY | |||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
0005 | TEMPORARY SIGNS | 02562 | SQFT | 230.00 | 230.000 | 233.000 | 233.000 | 5.00 | 1,165.00 | |||
0010 | MAINTAIN & CONTROL TRAFFIC (HARDIN COUNTY) | 02650 | LS | 1.00 | 1.000 | 0.200 | 0.200 | 118,000.00 | 23,600.00 | |||
0015 | SHOULDER RUMBLE STRIPS | 02696 | LF | 6,400.00 | 15,524.000 | 0.000 | 0.000 | 0.25 | 0.00 | |||
0020 | ARROW PANEL | 02775 | EACH | 4.00 | 4.000 | 3.000 | 3.000 | 424.00 | 1,272.00 | |||
0025 | PIEZOELECTRIC SENSOR (PLANNING LOOPS) | 04829 | EACH | 6.00 | 6.000 | 0.000 | 0.000 | 2,675.00 | 0.00 | |||
0030 | LOOP SAW SLOT AND FILL (PLANNING LOOPS) | 04895 | LF | 60.00 | 60.000 | 0.000 | 0.000 | 12.00 | 0.00 | |||
0035 | PAVE STRIPING REMOVAL-6 IN | 06531 | LF | 114,550.00 | 114,550.000 | 30,502.000 | 30,242.000 | 60,744.000 | 0.65 | 19,826.30 | 39,483.60 | |
0040 | PAVE STRIPING-THERMO-6 IN W | 06542 | LF | 66,618.00 | 66,618.000 | 0.000 | 0.000 | 1.35 | 0.00 | |||
0045 | PAVE STRIPING-THERMO-6 IN Y | 06543 | LF | 47,932.00 | 47,932.000 | 0.000 | 0.000 | 1.35 | 0.00 | |||
0050 | PAVE STRIPING-THERMO-12 IN W | 06546 | LF | 3,280.00 | 3,280.000 | 0.000 | 0.000 | 3.50 | 0.00 | |||
0055 | PAVE MARKING-THERMO STOP BAR-24IN | 06568 | LF | 70.00 | 70.000 | 0.000 | 0.000 | 15.00 | 0.00 | |||
0060 | LAW ENFORCEMENT OFFICER | 20411ED | HOUR | 160.00 | 160.000 | 103.000 | 24.500 | 127.500 | 120.00 | 12,360.00 | 15,300.00 | |
0065 | OVERBAND CRACK SEALING | 23071EN | LB | 30,000.00 | 30,000.000 | 13,521.952 | 13,521.952 | 1.70 | 22,987.31 | |||
0070 | INLAID PAVEMENT MARKER | 24489EC | EACH | 1,134.00 | 1,134.000 | 0.000 | 0.000 | 22.00 | 0.00 | |||
0075 | PAVE MARK THERMO-WRONG WAY ARROW | 24689EC | EACH | 4.00 | 4.000 | 0.000 | 0.000 | 400.00 | 0.00 | |||
0080 | REMOVE PAVEMENT MARKER | 24880EC | EACH | 1,134.00 | 1,134.000 | 748.000 | 0.000 | 748.000 | 15.32 | 11,459.36 | 11,459.36 | |
0085 | QUEUE PROTECTION VEHICLE | 25075EC | HOUR | 150.00 | 150.000 | 0.000 | 0.000 | 57.11 | 0.00 | |||
0090 | FURNISH QUEUE PROTECTION VEHICLES | 25117EC | MONT | 2.00 | 2.000 | 0.000 | 0.000 | 8,968.51 | 0.00 | |||
0095 | PORTABLE QUEUE WARNING ALERT SYSTEM | 26136EC | MONT | 2.00 | 2.000 | 1.000 | 0.500 | 1.500 | 4,268.28 | 4,268.28 | 6,402.42 | |
0100 | QUEUE WARNING PCMS | 26137EC | MONT | 6.00 | 10.000 | 5.000 | 2.500 | 7.500 | 1.00 | 5.00 | 7.50 | |
0105 | QUEUE WARNING PORTABLE RADAR SENSORS | 26138EC | MONT | 12.00 | 12.000 | 6.000 | 3.000 | 9.000 | 1.00 | 6.00 | 9.00 | |
0140 | MOBILIZATION FOR MILL & TEXT (HARDIN COUNTY) | 02676 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 25,000.00 | 0.00 | |||
0180 | PORTABLE CHANGEABLE MESSAGE SIGN (ADDED 1-15-25) | 02671 | EACH | 2.00 | 2.000 | 0.000 | 0.000 | 424.00 | 0.00 | |||
0185 | ASPHALT PAVE MILLING & TEXTURING | 02677 | TON | 55.00 | 55.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
Project | MP04700652501 | Fed/State Project Number | NHPM 0653(051) | Category | 0003 THINLAY | |||||||
0135 | ASPHALT MATERIAL FOR TACK | 00356 | TON | 88.00 | 88.000 | 0.000 | 0.000 | 0.01 | 0.00 | |||
0150 | PAVE STRIPING-TEMP PAINT-4 IN (THINLAY) | 06510 | LF | 138,000.00 | 138,000.000 | 64,051.500 | 45,150.000 | 109,201.500 | 0.31 | 19,855.96 | 33,852.46 | |
0155 | FIBER REINFORCEMENT FOR SURF NO.4 | 25054EC | TON | 8,500.00 | 8,500.000 | 0.000 | 0.000 | 7.50 | 0.00 | |||
0160 | CL4 ASPH SURF NO.4A PG64-22 | 25077EC | TON | 8,500.00 | 8,500.000 | 0.000 | 0.000 | 100.00 | 0.00 | |||
0175 | LEVELING & WEDGING PG76-22 (REVISED 1-15-25) | 00194 | TON | 67.00 | 67.000 | 23.380 | 0.000 | 23.380 | 250.00 | 5,845.00 | 5,845.00 | |
Project | MP04700652501 | Fed/State Project Number | NHPM 0653(051) | Category | 0004 DEMOBILIZATION | |||||||
0165 | MOBILIZATION | 02568 | LS | 1.00 | 1.000 | 0.500 | 0.500 | 165,000.00 | 82,500.00 | |||
0170 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 35,416.68 | 0.00 | |||
SUBTOT | $73,625.90 |
$243,883.663 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | 0.00 |
$0.000 |
Project | MP05000652501 | Fed/State Project Number | NHPM 0653(049) | Category | 0001 ROADWAY | |||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
0175 | TEMPORARY SIGNS | 02562 | SQFT | 230.00 | 230.000 | 233.000 | 233.000 | 5.00 | 1,165.00 | |||
0180 | MAINTAIN & CONTROL TRAFFIC (HART COUNTY) | 02650 | LS | 1.00 | 1.000 | 0.100 | 0.100 | 0.200 | 100,000.43 | 10,000.04 | 20,000.08 | |
0185 | SHOULDER RUMBLE STRIPS | 02696 | LF | 15,600.00 | 26,823.000 | 0.000 | 0.000 | 0.25 | 0.00 | |||
0190 | ARROW PANEL | 02775 | EACH | 4.00 | 4.000 | 4.000 | 0.000 | 4.000 | 424.00 | 1,696.00 | 1,696.00 | |
0195 | PIEZOELECTRIC SENSOR (PLANNING LOOPS) | 04829 | EACH | 12.00 | 12.000 | 0.000 | 0.000 | 2,675.00 | 0.00 | |||
0200 | LOOP SAW SLOT AND FILL (PLANNING LOOPS) | 04895 | LF | 120.00 | 120.000 | 0.000 | 0.000 | 12.00 | 0.00 | |||
0205 | PAVE STRIPING REMOVAL-6 IN | 06531 | LF | 271,180.00 | 271,180.000 | 117,305.000 | 117,295.000 | 234,600.000 | 0.65 | 76,248.25 | 152,490.00 | |
0210 | PAVE STRIPING-THERMO-6 IN W | 06542 | LF | 160,596.00 | 160,596.000 | 0.000 | 0.000 | 1.35 | 0.00 | |||
0215 | PAVE STRIPING-THERMO-6 IN Y | 06543 | LF | 110,584.00 | 110,584.000 | 0.000 | 0.000 | 1.35 | 0.00 | |||
0220 | PAVE STRIPING-THERMO-12 IN W | 06546 | LF | 3,050.00 | 3,050.000 | 0.000 | 0.000 | 3.50 | 0.00 | |||
0225 | PAVE MARKING-THERMO STOP BAR-24IN | 06568 | LF | 110.00 | 110.000 | 0.000 | 0.000 | 15.00 | 0.00 | |||
0230 | LAW ENFORCEMENT OFFICER | 20411ED | HOUR | 160.00 | 160.000 | 73.500 | 35.500 | 109.000 | 120.00 | 8,820.00 | 13,080.00 | |
0235 | OVERBAND CRACK SEALING | 23071EN | LB | 90,000.00 | 90,000.000 | 41,819.840 | 41,819.840 | 1.70 | 71,093.72 | |||
0240 | PAVE STRIPE-WET REF TAPE-6 IN Y | 23871EC | LF | 410.00 | 410.000 | 0.000 | 0.000 | 8.00 | 0.00 | |||
0245 | PAVE STRIPE-WET REF TAPE-6 IN W | 23872EC | LF | 615.00 | 615.000 | 0.000 | 0.000 | 8.00 | 0.00 | |||
0250 | INLAID PAVEMENT MARKER | 24489EC | EACH | 2,567.00 | 2,567.000 | 0.000 | 0.000 | 22.00 | 0.00 | |||
0255 | PAVE MARK THERMO-WRONG WAY ARROW | 24689EC | EACH | 4.00 | 4.000 | 0.000 | 0.000 | 400.00 | 0.00 | |||
0260 | REMOVE PAVEMENT MARKER | 24880EC | EACH | 2,567.00 | 2,567.000 | 79.000 | 0.000 | 79.000 | 15.32 | 1,210.28 | 1,210.28 | |
0265 | QUEUE PROTECTION VEHICLE | 25075EC | HOUR | 150.00 | 150.000 | 0.000 | 0.000 | 57.11 | 0.00 | |||
0270 | FURNISH QUEUE PROTECTION VEHICLES | 25117EC | MONT | 2.00 | 2.000 | 0.000 | 0.000 | 8,968.51 | 0.00 | |||
0275 | PORTABLE QUEUE WARNING ALERT SYSTEM | 26136EC | MONT | 2.00 | 2.000 | 0.500 | 0.000 | 0.500 | 4,268.28 | 2,134.14 | 2,134.14 | |
0280 | QUEUE WARNING PCMS | 26137EC | MONT | 2.00 | 10.000 | 2.500 | 0.000 | 2.500 | 1.00 | 2.50 | 2.50 | |
0285 | QUEUE WARNING PORTABLE RADAR SENSORS | 26138EC | MONT | 6.00 | 12.000 | 3.000 | 0.000 | 3.000 | 1.00 | 3.00 | 3.00 | |
0320 | MOBILIZATION FOR MILL & TEXT (HART COUNTY) | 02676 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 25,000.00 | 0.00 | |||
0360 | PORTABLE CHANGEABLE MESSAGE SIGN (ADDED 1-15-25) | 02671 | EACH | 2.00 | 2.000 | 0.000 | 0.000 | 424.00 | 0.00 | |||
0365 | ASPHALT PAVE MILLING & TEXTURING | 02677 | TON | 130.00 | 130.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
Project | MP05000652501 | Fed/State Project Number | NHPM 0653(049) | Category | 0003 THINLAY | |||||||
0315 | ASPHALT MATERIAL FOR TACK | 00356 | TON | 232.00 | 232.000 | 0.000 | 0.000 | 0.01 | 0.00 | |||
0330 | PAVE STRIPING-TEMP PAINT-4 IN (THINLAY) | 06510 | LF | 325,000.00 | 325,000.000 | 159,943.500 | 141,718.000 | 301,661.500 | 0.31 | 49,582.48 | 93,515.06 | |
0335 | FIBER REINFORCEMENT FOR SURF NO.4 | 25054EC | TON | 22,700.00 | 22,700.000 | 0.000 | 0.000 | 7.50 | 0.00 | |||
0340 | CL4 ASPH SURF NO.4A PG64-22 | 25077EC | TON | 22,700.00 | 22,700.000 | 0.000 | 0.000 | 100.00 | 0.00 | |||
0355 | LEVELING & WEDGING PG76-22 (REVISED 1-15-25) | 00194 | TON | 67.00 | 67.000 | 0.260 | 0.000 | 0.260 | 250.00 | 65.00 | 65.00 | |
Project | MP05000652501 | Fed/State Project Number | NHPM 0653(049) | Category | 0004 DEMOBILIZATION | |||||||
0345 | MOBILIZATION | 02568 | LS | 1.00 | 1.000 | 0.500 | 0.500 | 165,000.00 | 82,500.00 | |||
0350 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 35,416.66 | 0.00 | |||
SUBTOT | $149,761.69 |
$438,954.799 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | 0.00 |
$0.000 |
Project | MP06200652501 | Fed/State Project Number | NHPM 0653(050) | Category | 0001 ROADWAY | |||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
0355 | TEMPORARY SIGNS | 02562 | SQFT | 230.00 | 230.000 | 32.000 | 32.000 | 5.00 | 160.00 | |||
0360 | MAINTAIN & CONTROL TRAFFIC (LARUE) | 02650 | LS | 1.00 | 1.000 | 0.200 | 0.100 | 0.300 | 105,000.00 | 21,000.00 | 31,500.00 | |
0365 | SHOULDER RUMBLE STRIPS | 02696 | LF | 5,100.00 | 5,100.000 | 0.000 | 0.000 | 0.25 | 0.00 | |||
0370 | ARROW PANEL | 02775 | EACH | 4.00 | 4.000 | 0.000 | 0.000 | 424.00 | 0.00 | |||
0375 | PAVE STRIPING REMOVAL-6 IN | 06531 | LF | 127,750.00 | 127,750.000 | 70,408.000 | 30,312.000 | 100,720.000 | 0.65 | 45,765.20 | 65,468.00 | |
0380 | PAVE STRIPING-THERMO-6 IN W | 06542 | LF | 74,538.00 | 74,538.000 | 0.000 | 0.000 | 1.35 | 0.00 | |||
0385 | PAVE STRIPING-THERMO-6 IN Y | 06543 | LF | 53,212.00 | 53,212.000 | 0.000 | 0.000 | 1.35 | 0.00 | |||
0390 | PAVE STRIPING-THERMO-12 IN W | 06546 | LF | 3,520.00 | 3,520.000 | 0.000 | 0.000 | 3.50 | 0.00 | |||
0395 | PAVE MARKING-THERMO STOP BAR-24IN | 06568 | LF | 180.00 | 180.000 | 0.000 | 0.000 | 15.00 | 0.00 | |||
0400 | OVERBAND CRACK SEALING | 23071EN | LB | 35,000.00 | 35,000.000 | 26,558.204 | 26,558.204 | 1.70 | 45,148.94 | |||
0405 | INLAID PAVEMENT MARKER | 24489EC | EACH | 1,200.00 | 1,200.000 | 0.000 | 0.000 | 22.00 | 0.00 | |||
0410 | PAVE MARK THERMO-WRONG WAY ARROW | 24689EC | EACH | 4.00 | 4.000 | 0.000 | 0.000 | 400.00 | 0.00 | |||
0415 | REMOVE PAVEMENT MARKER | 24880EC | EACH | 1,200.00 | 1,200.000 | 88.000 | 0.000 | 88.000 | 15.32 | 1,348.16 | 1,348.16 | |
0450 | MOBILIZATION FOR MILL & TEXT (LARUE) | 02676 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 25,000.00 | 0.00 | |||
0480 | PORTABLE CHANGEABLE MESSAGE SIGN (ADDED 1-15-25) | 02671 | EACH | 2.00 | 2.000 | 0.000 | 0.000 | 424.00 | 0.00 | |||
0485 | ASPHALT PAVE MILLING & TEXTURING | 02677 | TON | 55.00 | 55.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
Project | MP06200652501 | Fed/State Project Number | NHPM 0653(050) | Category | 0003 THINLAY | |||||||
0440 | LEVELING & WEDGING PG76-22 (REVISED 1-15-25) | 00194 | TON | 67.00 | 67.000 | 2.390 | 0.000 | 2.390 | 250.00 | 597.50 | 597.50 | |
0445 | ASPHALT MATERIAL FOR TACK | 00356 | TON | 89.00 | 89.000 | 0.000 | 0.000 | 0.01 | 0.00 | |||
0460 | PAVE STRIPING-TEMP PAINT-4 IN (THINLAY) | 06510 | LF | 155,000.00 | 155,000.000 | 102,598.500 | 42,016.000 | 144,614.500 | 0.31 | 31,805.53 | 44,830.49 | |
0465 | FIBER REINFORCEMENT FOR SURF NO.4 | 25054EC | TON | 8,650.00 | 8,650.000 | 0.000 | 0.000 | 7.50 | 0.00 | |||
0470 | CL4 ASPH SURF NO.4A PG64-22 | 25077EC | TON | 8,650.00 | 8,650.000 | 0.000 | 0.000 | 100.00 | 0.00 | |||
Project | MP06200652501 | Fed/State Project Number | NHPM 0653(050) | Category | 0004 DEMOBILIZATION | |||||||
0475 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 35,416.66 | 0.00 | |||
SUBTOT | $100,516.39 |
$189,053.101 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | 0.00 |
$0.000 |